AMOUNT AND COST OF WORK
| Bronx | Queens | Richmond | Totals |
Population (1910) | 430,980 | 283,041 | 85,969 |
Total area in acres | 26,523 | 75,111 | 36,480 | 138,114 |
Triangulation (in acres) | 26,523 | 75,111 | 36,430 | 138,114 |
Topographical Survey (in acres) | 26,523 | 55,188 | 18,430 | 100,141 |
Tentative Street Maps Approved (in acres) | 18,700 | 19,661 | 6,300 | 44,661 |
Final Maps Adopted (in acres) | 13,000 | 9,912 | 6,300 | 29,212 |
Expenditures 1902-1909 | $779,916 | $1,281,946 | $839,975 | $2,901,837 |
Recommended for 1910 | $160,395 | $362,752 | $218,000 | $705,147 |
On March 31, 1910, the forces of the several topographical Bureaus of New York were as follows:
| Bronx | Queens | Brooklyn | Richmond | Totals |
Engineers in charge and principal
assistant engineers | 1 | 2 | 2 | 1 | 6 |
Assistant engineers | 17 | 15 | 16 | 17 | 65 |
Transitmen, computers and draftsmen | 26 | 53 | 17 | 41 | 137 |
Chainmen, rodmen, axemen and
levelers | 21 | 18 | 12 | 17 | 68 |
Clerical | 3 | 6 | 5 | 2 | 16 |
Laborers | 7 | 62 | 11 | 25 | 105 |
Foremen, drivers and others | 3 | 15 | 2 | 8 | 28 |
Total | 78 | 171 | 65 | 111 | 425 |
Expenses recommended for 1910 | $160,395 | $326,752 | $80,000 | $218,000 | $785,147 |
The work is expected to be so far advanced as to permit of material reductions in the present staffs at the following dates: in the Bronx, December 1911; in Queens, April 1915; in Brooklyn, April 1913; in Richmond, June 1911.
A detailed analysis of the cost of the work in the Borough of Queens, dated October 14, 1910, is subjoined:
| Cost per acre to date | Estimated cost per acre of completed work |
Topographical Survey including preparation of maps of street system and grades |
Field | $ 8.13 | Field | $ 8.06 |
Office | $ 2.23 | Office | $ 2.23 |
Total | $10.36* | Total | $10.29 |
Monumenting, including final traversing and preparation of final map sections |
Field | $27.92 | Field | $20.44 |
Office | $10.89 | Office | $ 7.89 |
Total | $38.81 | Total | $28.33 |
*The difference between the cost per acre to date and the estimated cost per acre of completed work is due to the initial cost of organization and to the cost of general work such as triangulation and traversing, which must be done at the start for the whole or most of the area to be surveyed.